Project Tracker
Smith Residence
28 Maple Avenue, Chatham NJ
← All Projects
Total Tasks
186
Across 12 phases
Overall Progress
42%
Modified
3
Unsaved changes
Last Saved
Apr 7, 2:14 PM
Synced to Smartsheet
Sitework & Foundation
100%
Framing
100%
Rough Mechanicals
62%
Electrical Rough-In — First Floor
Apr 8 → Apr 14
100%
Electrical Rough-In — Second Floor
Apr 14 → Apr 18
75%
Rough Plumbing — First Floor
Apr 14 → Apr 19
100%
Rough Plumbing — Second Floor
Apr 21 → Apr 25
75%
HVAC Ductwork — Main Trunk
Apr 22 → Apr 28
50%
Summit HVAC
5 days
% Done
0
25
50
75
100
HVAC Branch Runs — Second Floor
Apr 28 → May 2
25%
Fire Suppression Rough
May 1 → May 3
0%
Insulation & Drywall
0%
Interior Finish
0%
Punch & Final
0%
3 unsaved changes