| Task Name | Start Date | Duration | Progress |
|---|---|---|---|
| Rough Plumbing — First Floor | Apr 14 | 5 days | 100% |
| Rough Plumbing — Second Floor | Apr 21 | 4 days | 75% |
| Plumbing Top-Out | May 5 | 2 days | 0% |
| Plumbing Trim & Fixtures | Jul 28 | 6 days | 0% |
| Task Name | Start Date | Duration | Progress |
|---|---|---|---|
| Demo Existing Plumbing | Apr 8 | 2 days | 100% |
| Rough-In New Lines | Apr 15 | 3 days | 50% |
| Final Connections & Test | May 20 | 2 days | 0% |
| Task Name | Start Date | Duration | Progress |
|---|---|---|---|
| Tie-In to Existing Plumbing | May 12 | 3 days | 0% |
| New Bathroom Rough-In | May 19 | 4 days | 0% |
| Task Name | Start Date | Duration | Progress |
|---|---|---|---|
| Bathroom Rough Plumbing | Jun 2 | 3 days | 0% |
| Wet Bar Connections | Jun 9 | 1 day | 0% |